The long-awaited New Richmond Bridge has reached another major milestone, with the NSW and Australian Governments finalising environmental approval for Stage 2 and awarding the design and construction contract.
The announcement confirms the full $658 million project is now progressing, with construction of Stage 2 expected to begin in late 2026 and be completed in 2029.
The project aims to ease congestion between Richmond and North Richmond, improve flood resilience and provide a safer crossing of the Hawkesbury River.
Community concerns change project delivery
One of the biggest changes announced by Transport for NSW is that Stage 2 will no longer be split into separate construction phases.
Following strong community feedback during public consultation, particularly from residents living along Southee Road and in Hobartville, the Australian and NSW Governments committed an additional $143 million so that Stages 2A and 2B can be built together as a single project.
Transport for NSW said this change responds directly to concerns about the impacts a staged approach would have had on local residents.
What will be built?
When construction begins, Stage 2 will include:
- a new four-lane bridge across the Hawkesbury River
- widening of Bells Line of Road through North Richmond
- upgrades to the Bells Line of Road intersection with Grose Vale Road and Terrace Road
- a new bypass linking Kurrajong Road and Old Kurrajong Road to Londonderry Road via Inalls Lane
- a separated section running parallel to Southee Road with landscaping and noise mitigation
- new walking and cycling links connecting Richmond and North Richmond.
Artist impressions released with the update also show how the existing Richmond Bridge will be converted into a dedicated walking and cycling connection once the new bridge opens.
Environmental approval complete
Transport for NSW has completed and determined the project's Review of Environmental Factors (REF), giving the project environmental approval to proceed.
The REF was publicly exhibited between December 2024 and February 2025, during which Transport received submissions from residents, businesses, community organisations and government agencies.
What residents said
Transport says the major issues raised during consultation included:
- concerns about staging the project
- flooding and drainage impacts
- traffic congestion
- construction and operational noise
- heritage impacts
- pedestrian and cycling connections
- how the preferred route was selected.
In response, Transport has committed to:
- constructing Stages 2A and 2B together;
- refining walking and cycling paths to improve safety and connectivity; and
- reviewing bridge and drainage designs to minimise flood impacts.
Investigation work continues
Before major construction begins, crews will undertake additional site investigations, including:
- geotechnical testing
- utility investigations
- Aboriginal heritage surveys
- non-Aboriginal archaeological investigations.
Transport also confirmed it has contacted landowners affected by property acquisition and will continue discussions as the project progresses.

Stage 1 progressing
Meanwhile, Stage 1 of the New Richmond Bridge project is already underway.
This stage involves upgrades to intersections along The Driftway at Blacktown Road and Londonderry Road to improve safety and flood resilience.
Construction of Stage 1 is expected to be completed in 2027.
A project decades in the making
For many Hawkesbury residents, the announcement represents another significant milestone in a project that has been discussed for decades.
Once complete, the New Richmond Bridge is expected to:
- reduce congestion at one of the Hawkesbury's busiest river crossings;
- improve access during flood events;
- enhance road safety;
- provide dedicated walking and cycling infrastructure; and
- improve travel reliability for residents, businesses and emergency services.
Construction of the main bridge and associated roadworks is expected to commence in late 2026, with the full Stage 2 project scheduled for completion in 2029.

Key Dates
- $658 million committed by the Australian and NSW Governments
- Additional $143 million secured to deliver Stages 2A and 2B together
- Environmental approval: Finalised
- Design and construction contract: Awarded
- Stage 2 construction: Expected to commence late 2026
- Stage 1 completion: Expected in 2027
- Stage 2 completion: Expected in 2029
If you have any questions, please email richmondbridge@transport.nsw.gov.au or call 1800 370 778.
All images supplied by Transport NSW